Vietnam - My Phuoc – Tan Van Expressway Project

About this project
The route starts from the My Phuoc Industrial and Urban area and passes through large industrial parks located in 4 districts and towns (Ben Cat, Thu Dau Mot City, Thuan An and Di An) to the international airport and seaport. Roads are designed accordingly to high-quality motorway standards. When completed, it will connect with the Trans-Asia road, Ho Chi Minh road, and the transportation system of the whole Southern Key Economic region. The total length of the route is 42 km; 30 km for the main road and 12 km of roads connecting to bridges and intersections to connect externally. Investment Method: BOT. Total Investment: 3,500 billion VND Construction period is 4 years. Construction started on August 7th, 2009.